| Activity | Predecessor | Time (weeks) | Slack | Critical? |
| A | - | 6 | ||
| B | - | 8 | ||
| C | A | 12 | ||
| D | A,B | 4 | ||
| E | C | 6 | ||
| F | D,E | 15 | ||
| G | E | 12 | ||
| H | F,G | 8 |
Compute the standard deviation of the time for completion of the entire project.
Optimistic: 5
Most Probable: 7
Pessimistic: 12
What is the expected completion time of the project?